Towamba and Burragate Road Upgrade

The upgrade and sealing of Towamba and Burragate Roads to enable all weather access from these outlying villages to the larger commercial hubs of Eden, Bombala and Pambula.


Project summary/background

Bega Valley Shire Council was successful in securing a one-off grant from the NSW Government of $10 million for the upgrade and sealing of Towamba and Burragate Roads. The total length of the two roads is 47.4km, of which 25km is currently unsealed road; 20.4km on Towamba Road and 4.6km on Burragate Road.

The Towamba and Burragate communities are highly supportive of this project as it will enable all weather access from these outlying villages to the larger commercial hubs of Eden, Bombala and Pambula. The Towamba Valley is prone to serious flooding events and the current road condition may increase emergency response and evacuation times.

Council currently has 121 properties addressed from Towamba and Burragate Roads; and the route is used by school buses for students traveling to Eden and Pambula for secondary schooling.

Sealing of both Towamba and Burragate Roads is required to be completed by the 1 March 2022 to meet the NSW Government funding deadline.

Purpose

The project intent is to seal the full length of both Towamba and Burragate Roads. This project includes sealing and resealing, pavement stabilisation, new guardrails and drainage works to improve the safety and driveability of the two roads.

Funding

This project is 100% funded by a one-off grant of $10 million from the NSW State Government.

Connection to Council's Community Strategic Plan

This project is connected to Council's Community Strategic Plan through Outcome 2; Goal 3; Strategy 6.

  • Outcome 2: Employment and Learning Opportunities
  • Goal 3: Our economy is prosperous, diverse and supported by innovative and creative businesses.
  • Strategy 6: Collaborate with relevant parties to develop and enhance the economic opportunities provided by the development of the Port of Eden, Merimbula Aiport, East West freight corridor, and tourism services and facilities.

Link to NSW Government.

 

Who to talk to:

Daniel Djikic
Manager Project Services
Bega Valley Shire Council
Phone: (02) 6499 2222
Email: council@begavalley.nsw.gov.au

 

Timeline of works


  • March 2019

    Funding received from NSW State Government.

  • April - June 2019

    Project scoping

  • July - September 2019

    Project Management / Design Consultant Tender

  • October 2019

    GHD Pty Ltd engaged as Project Management / Design Consultant

  • November 2019 - January 2020

    Feasibility Report, Site Survey and Investigations

  • February - June 2020

    Detailed Design

  • July - October 2020

    Construction Tender

  • November 2020 - March 2022

    Construction Works

  • March 2022

    Target deadline.

  • April 2022

    Works completed.

  • April 2023

    Defect warranty period ends.


News and Updates

Monthly Communications Update - Towamba and Burragate Road Upgrade Project

 

Contact Us