Katchencarry Creek Bridge Replacement

Replacement of the old single lane timber bridge over Katchencarry Creek with a new dual-lane concrete bridge.


A water main crossing Katchencarry Creek bridge

Background and Purpose

This project will replace the timber bridge over Katchencarry creek on Upper Brogo Road.

The existing single-lane timber bridge will be replaced with a new 18.5m span dual lane concrete InQuik bridge.

The new bridge will be constructed by Council’s own Bridge Team who have recently completed installing a smaller bridge using the same methods on Wandella Road.

The new concrete bridge will be more resilient to natural disasters such as fire and flooding, ensuring Upper Brogo Road can be reopened sooner following major weather events.

It will also improve traffic flow and will ease future maintenance burden.

Project update

As part of the Katchencarry Creek Bridge Replacement project, the Water and Sewer team is nearing completion of works to relocate an existing watermain currently situated in the creek, with around 95% of works on this part of the project now complete.

The works include securing a new 250mm ductile pipe to the bridge using specially designed, custom-made brackets. This allows the existing main to be removed from the creek and reduces the risk of damage to the pipe during flood events.

With a 100-year design life, the new pipe will deliver reliable service well into the future. The upgrade is funded through Council’s Water Fund and forms an important part of supplying treated water from Brogo Water Treatment Plant to the local community.

Funding

The project is fully funded by the Transport for NSW Fixing Country Bridges Program, with the estimated project cost being $1.8 million.

Connection to Council's Community Strategic Plan

This project aligns with Bega Valley Shire Council Community Strategic Plan through:

  • D.1 Plan for community infrastructure and services that will meet current and future needs.
  • D.2. Provide infrastructure and services to meet the needs of residents in our towns, villages and rural areas.
  • D.3 Improve the presentation, maintenance and physical accessibility of existing towns and villages.
  • Delivery Program 2022 - 2025:
  • D1.1 – Plan for asset capital works.
  • D2.3 - Construct (upgrade or renewal) civil assets / infrastructure.

 

Who to talk to

Cheyne Dick-Lenehan   
Project Manager
Bega Valley Shire Council
Phone: 0403 739 326
Email: cdick-lenehan@begavalley.nsw.gov.au

 

Timeline of works


  • Early December 2024

    Site establishment and works commencing

  • January to April 2025

    Construction and road closure

  • May 2025

    Works complete


Frequently Asked Questions


The road will need to be closed for the duration of the works, which is likely to be around three months, from Monday 9 December 2024 to March 2025, weather permitting.

The new bridge will have two lanes.


 