Murrays Creek bridge replacement

The project involves replacing the existing single-lane timber bridge with a modern single-span, two-lane concrete bridge and improving the road alignment. A bypass track and temporary bridge have been constructed to avoid road closures.


Murrays creek bridge.

 

Project summary

The existing single-span timber bridge over Murrays Creek on Buckajo Road is being replaced as part of Transport for New South Wales’ Fixing Country Bridges program.

The new bridge will be a 12-metre single-span concrete structure, slightly higher than the existing timber bridge. It will be installed by Council’s bridge team.. Following installation, the road alignment will be updated to match the new bridge.

Purpose

The existing timber bridge has reached the end of its useable lifespan and required regular maintenance to remain safe for road users.

The new concrete bridge is designed for a 100-year lifespan and will require only minimal maintenance during this period. It is also far more resilient to natural disasters such as fire and flooding.

Funding

The project is fully funded through Transport for New South Wales’ Fixing Country Bridges program.

Connection to Council's Community Strategic Plan

This project aligns with Bega Valley Shire Council Community Strategic Plan through:

  • D.1 Plan for community infrastructure and services that will meet current and future needs.
  • D.2. Provide infrastructure and services to meet the needs of residents in our towns, villages and rural areas.
  • D.3 Improve the presentation, maintenance and physical accessibility of existing towns and villages.
     

    Delivery Program 2022 - 2025:

  • D1.1 – Plan for asset capital works.
  • D2.3 - Construct (upgrade or renewal) civil assets / infrastructure.

Who to talk to

Cheyne Dick-Lenehan
Project Management
Bega Valley Shire Council
Phone: (02) 6499 2222
Email: cdick-lenehan@begavalley.nsw.gov.au

 

Timeline of works


  • June

    Installation of side track and temporary bridge

  • July

    Demolition of the existing bridge, piling works and installation of the new bridge

  • August

    Approach road works, opening of new bridge, removal of side track and temporary bridge, reinstatement of the surrounding area