The closure of Merimbula Airport has been extended to 25 March due to rain delays.
4 March 2022
The closure of Merimbula Airport has been extended to 25 March due to rain delays.
Project Services Manager, Daniel Djikic said Council has been working closely with the contractor to identify the most effective way to complete the works with the least impact on the community and airlines.
“We’ve looked at a number of scenarios to complete the work as close to the original schedule as possible, but with the amount of rain we’ve had, and more rain forecast, we’ve had to plan for a 10-day extension to the airport closure,” Mr Djikic said.
“We know this is inconvenient for travellers, the airlines and the broader community, but unfortunately we are at the mercy of the weather and there’s not much we can do.
“If anything changes with the weather that will impact the planned re-opening date, we will inform the airlines and the community as soon as possible.
“Work is still being carried out on-site in preparation for the sealing to re-start. All being well, this should start again on Thursday 10 March.”
The north and south runway extensions have been completed, the taxiways and apron have been strengthened and stabilised, and about 80% of the runway has been sealed with its first coat.
The sealing of the remainder of the runway, taxiways and apron will commence once the pavement has sufficiently dried out, followed by line marking and final safety checks before the airport re-opens.
Council has been working closely with the airlines and emergency services throughout the project and would like to thank the community for their patience.
The runway extension and strengthening project is funded through two grants from the Commonwealth Government, two grants from the NSW Government and a Council contribution.
More information about the project is available on Council’s website.
All media enquiries and interview requests are coordinated by Council's Communication and Engagement team under the adopted Communications Policy. To view this policy, visit Public Policies and search 'communications'.
To submit a media enquiry or to request an interview:
Councillors can be contacted directly for enquiries regarding decisions of the elected Council and non-operational matters. Interviews with the Mayor should be arranged through the Communication and Engagement team contact details above.
If you’re a journalist or media organisation that would like to receive media releases and notifications about media opportunities, please email your name, title and contact details to media@begavalley.nsw.gov.au and we will add you to our distribution list.
You can also subscribe to Bega Valley Together and Business News, Council's fortnightly e-newsletters, or follow @begavalleyshirecouncil on Facebook and Instagram.
Zingel Place
PO Box 492
Bega NSW 2550
Monday to Friday 9.00AM to 4.30PM
Administration building Zingel Place Bega
Australia
ABN: 26 987 935 332