Information about Council's regular services and programs.
Information about Council's community initiatives and support.
Information about doing business and investing in the shire.
Information about Building and Development in the Bega Valley Shire.
Information about how Council operates.
The Watergums Creek Bridge upgrade will improve access and resilience for the Wonboyn community.
The Watergums Creek Bridge upgrade will improve access and resilience for the Wonboyn community and all traffic passing over the bridge.
The new bridge design considers the flood conditions of the Wonboyn River and Watergums Creek, and the existing level of service of Wonboyn Road in order to maintain access for road users between Wonboyn and the Princes Highway during flood events.
The recent, prolonged rainfall experienced in the Bega Valley resulted in Watergums Creek Bridge being inundated on 8 separate occasions from July 2020 to April 2022, resulting in closure of Wonboyn Road for total duration of 20 days. On four of these occasions, the bridge was inundated by more than two metres.
The new bridge will:
The main purpose of this project is to:
The design of the new bridge will:
Construction will involve:
Enviornmental controls will applied through:
This project is funded by the Australian Government with a contribution by Bega Valley Shire Council.
The Australian Government has funded $3.54M of this project under the Bridges Renewal Program.
Bega Valley Shire Council is contributing $1M to this project, from funds contributed by the NSW Government following the declared natural disaster of severe weather and flooding in February and March 2022 (AGRN 1012).
This project aligns with Bega Valley Shire Council Community Strategic Plan through:
Cheyne Dick-Lenehan
A/Technical Services Coordinator
Bega Valley Shire Council
Phone: (02) 6499 2222
Email: CDick-Lenehan@begavalley.nsw.gov.au
Council intends to complete construction during 2025. The proposed timeframe is:
Project Planning, Environmental Reports and Detailed Design.
Undertake Procurement Activities for Construction.
Construction Planning Activities.
Proposed Construction Period.
The project is now complete with the bridge opening to traffic just before the Christmas school holidays.
Wonboyn River Bridge was replaced under the NSW Governments Fixing Country Bridges Program, which was a program dedicated for replacing aging timber bridges which are near the end of their practical lives. The program did not financially allow for infrastructure upgrades to meet recent flood levels.
Due to the length of the Wonboyn River Floodplain in this location, to raise the bridge an additional 1.0m, approximately 400m of roadworks would be required to raise the road approaches to the same level. This extent of works was not feasible based on the funding and scope of works approved under the Fixing Country Bridges Grant.
No, Wonboyn Road is flood affected in several locations due to the natural topography and road alignment.
Wonboyn Road will still be susceptible to flooding where it crosses the floodplain at Wonboyn River Bridge, and where Wonboyn Road runs adjacent to the Wonboyn River between Watergums Creek Bridge and the Wonboyn Village.
Currently Watergums Creek Bridge is the location where Wonboyn Road provides the lowest level of flood immunity.
Whilst Wonboyn Road will remain flood affected, the frequency and duration of road closures on Wonboyn Road will be reduced because of this upgrade.
The upgraded bridge will be on the existing road alignment of Wonboyn Road. Access to Wonboyn will be maintained via a bypass track and a single lane, temporary bailey-bridge which will operate under traffic lights for the duration of works.
The underside of the bridge has been designed to be 500mm above the estimated 5% annual flood event (historically referred to as the 20-year flood event). This results in the bridge deck being above the estimated 1% annual flood event (historically referred to as the 100-year flood event).
The upgraded bridge will be a reinforced concrete structure, resilient to bushfire threats and designed to withstand loading of flood forces and debris, with a design life of 100 years. The bridge will be designed and constructed to SM1600 loading, which accounts for the possibility of two multi-trailer trucks travelling in convey, in a traffic lane. The proposed bridge design includes two lanes - an improvement from the existing single-lane bridge.
Yes. We will ensure that there is clear, safe access to the water fill point located north of the bridge throughout the duration of the project.
For typical construction contracts the defects period is 12 months after works is complete. This has not yet been confirmed and will depend on the contracts for this project. Note that natural disasters such as flooding are not construction defects and are managed via a different process differently. Any defects that arise after the contractor liability period will be addressed by Council as the asset owner.
As part of the ‘Fisheries Management Act 1994 (FM Act)’ it is a requirement to submit a permit for any ‘Dredging, reclamation or barrier to fish passage in the waterway’. Council has been in consolation with Fisheries for this project to ensure that all items on concern are addressed and the project is managed in a safe and responsible manner as per the environmental legislation.
Our current estimates are 4-6 weeks for the removal of the debris which will include building a safe access to the stockpile. We are awaiting feedback from the contractor who will be completing the works.
There will be several procedures employed to monitor, manage and protect the bridge during construction works. Unfortunately the bridge will be vulnerable until construction is completed and the necessary protection is completed but this will be assessed to determine what other controls can be included.
Zingel Place
PO Box 492
Bega NSW 2550
Monday to Friday 9.00AM to 4.30PM
Administration building Zingel Place Bega
Australia
ABN: 26 987 935 332