Cobargo Park Street Recreation Upgrades

The design and construction of a BMX track, skatepark, netball/basketball court and carpark.


aerial shot of a carpark, skatepark and basketball court.

 

Project Summary

Cobargo Skatepark

The Cobargo Skatepark was a community project developed by the Cobargo Skate Club. The Club was successful in obtaining a grant from the NSW State Government and, along with other funds the club were able to raise and many hours of volunteer labour, the project was completed in 2012.

BMX Track

In 2018 the Cobargo Skate Club submitted a Community Project Proposal called ‘Baskets & Bikes’. The club worked with a large group of volunteers to build a BMX track using 1,000 tonnes of free landfill from the Dignams Creek bypass. It took just three weeks and was the result of almost 400 hours of volunteer time and assistance.

Netball/Basketball Court

In 2023, the Cobargo Skate Club and Cobargo Green Recovery Inc group worked on the second item of the ‘Baskets & Bikes’ community project being the development of a multi-use netball and basketball court.

This project was funded by a $109,178grant through the NSW State Government Bushfire Resilience and Recovery Fund program. Council staff supported the project through design and procurement advice.

Carpark

This project saw the delivery of a carpark upgrade, providing improved access to the basketball/netball court facility, skatepark and BMX track and the Narira Park sportsground.

The works included 30 new car parking spaces, including two accessible parking spaces, pavement repair, bitumen seal and line-marking.

This project was funded by a $100,000 grant through the Federal Government’s Investing in Our Communities program.

Connection to Council's Community Strategic Plan

This project aligns with Bega Valley Shire Council Community Strategic Plan through:

  • D - Our Infrastructure
  • D.5 - Collaborate with partners to provide open space, facilities, activities and services that encourage more people to have active and healthy lifestyles and improve accessibility to our natural environment
  • D5.4 - Undertake capital projects to improve recreation facilities, boating infrastructure, public toilets and sporting grounds and facilities.

Who to talk to

Sean Howle
Project Manager
Bega Valley Shire Council
Phone: 0436 921 043
Email: showle@begavalley.nsw.gov.au

 

Timeline of works


  • Cobargo Skatepark completed

    2012

  • BMX Track completed

    2018

  • Netball/Basketball Court completed

    2023

  • Carpark completed

    2025

  • Cobargo Park Street Recreation Upgrade full project completed

    2025